- A and B can do a work in 12 days, B and C in 30 days and C and A in 36 days. In how many days will the work be completed, if all three of them work together?
Answer : Option C
Explanation :
One day work of A and B = 1/12
One day work of B and C = 1/30
One day work of C and A = 1/36
2(A + B + C) = 1/12 + 1/30 + 1/36
2(A + B + C) = 13/90
(A + B + C) = 13/180
Number of days required = 180/13 days.