- A, B and C can do a work in 6 days, 8 days and 12 days respectively. In how many days can all three of them working together, complete the work?
Answer : Option A
Explanation :
Work done by all three of them in one day = 1/6 + 1/8 + 1/12 = 3/8.
The number of days required = 8/3 = 2 2/3 days.