Discussion :: Time and Work
- A and B can do a work in 5 days and 10 days respectively. A starts the work and B joins him after 2 days. In how many days can they complete the remaining work?
Answer : Option B
Explanation :
Work done by A in 2 days = 2/5
Remaining work = 3/5
Work done by both A and B in one day = 1/5 + 1/10 = 3/10
Remaining work = 3/5 * 10/3 = 2 days.
Be The First To Comment