Discussion :: Time and Work
- A can do a piece of work in 12 days. He worked for 15 days and then B completed the remaining work in 10 days. Both of them together will finish it in.
Answer : Option A
Explanation :
15/25 + 10/x = 1 => x = 25
1/25 + 1/25 = 2/25
25/2 = 12 1/2 days