  1. If 12 men do a work in 80 days, in how many days will 16 men do it?
  2. A.
    30
    B.
    40
    C.
    50
    D.
    60

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    12 * 80 = 16 * x

    x = 60 days