  1. 5 men and 12 boys finish a piece of work in 4 days, 7 men and 6 boys do it in 5 days. The ratio between the efficiencies of a man and boy is?
  2. A.
    1:2
    B.
    2:1
    C.
    2:3
    D.
    6:5

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    5M + 12B ----- 4 days

    7M + 6B ------- 5 days

    20M + 48B = 35M + 30B

    18B = 15M => 5M = 6B

    M: B = 6:5