  1. After fixing the plane table to the tripod, the main operations which are needed at each plane table station are
    (i) Levelling
    (ii) Orientation
    (iii) Centering
    The correct sequence of these operations is

  2. A.

     (i), (ii), (iii)

    B.

     (i), (iii), (ii)

    C.

     (iii), (i), (ii)

    D.

     (ii), (iii), (i)

    View Answer

    Workspace

    Answer : Option B