  1. While filling the tender for any work, the contractor considers

  2. A.

     Site survey

    B.

     Availability of construction materials

    C.

     Availability of labour

    D.

     All the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided