Home / Civil Engineering / Construction Planning and Mgmt :: Discussion

Discussion :: Construction Planning and Mgmt

  1. Critical path method

  2. A.

     Is an improvement upon bar chart method

    B.

     Provides a realistic approach to daily problems

    C.

     Avoids delays which are very common in bar charts

    D.

     All the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided