  1. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

  2. A.

     Started 5 days later

    B.

     Completed 5 days later

    C.

     Performed at slower rate in 15 days

    D.

     All the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    Explanation Not Provided